Pool construction involves many phases, inspections, and trades. Here's the realistic timeline and what happens at each stage.
Weeks 1-4: Permitting
Submit pool permit application. City review (2-4 weeks typical). Address any corrections. Receive permit approval. This phase varies most by jurisdiction. Some cities take 2 weeks, others 8+.
Week 5: Excavation
Pool shape is laid out. Excavation takes 1-3 days. Soil is removed (expect trucks). Rough shape of pool emerges. This is exciting but messy. Your yard will be a construction zone.
Ready to Start Your Project?
Schedule a free consultation with our design team.
Weeks 6-7: Steel & Plumbing
Rebar cage is tied. Plumbing lines installed. Electrical conduit run. Equipment pad formed. First inspection by city.
Week 8: Gunite/Shotcrete
Pool shell is sprayed. This is the loudest day. Shell needs to cure (water daily for 2 weeks). Rough shape complete.
Weeks 9-11: Tile, Coping, Decking
Waterline tile installed. Coping stones set. Pool deck poured or pavers installed. Equipment installed. Most visible progress happens here.
Weeks 12-14: Plaster & Startup
Interior finish applied. Pool fills with water (24-48 hours). Equipment startup and balancing. Homeowner orientation. First swim!
Final Thoughts
Expect 12-16 weeks total from permit to swimming. Weather delays, inspection schedules, and material availability can extend this. Patience is essential.
Frequently Asked Questions
Typically 12-16 weeks from permit approval to first swim.
Gunite/shotcrete day is the loudest. Warn your neighbors.




