Pool Construction Week by Week: What to Expect
See each stage, from permits and excavation to plaster and startup.
Remodel Your Vibe Design Team May 22, 20269 min read
Image: Pool construction phases timeline
In this article
- Weeks 1-4: Permitting
- Week 5: Excavation
- Weeks 6-7: Steel & Plumbing
- Week 8: Gunite/Shotcrete
- Weeks 9-11: Tile, Coping, Decking
- Weeks 12-14: Plaster & Startup
Pool construction involves many phases, inspections, and trades. Here's the realistic timeline and what happens at each stage.
In this article
- Weeks 1-4: Permitting
- Week 5: Excavation
- Weeks 6-7: Steel & Plumbing
- Week 8: Gunite/Shotcrete
- Weeks 9-11: Tile, Coping, Decking
- Weeks 12-14: Plaster & Startup
Weeks 1-4: Permitting
Submit pool permit application. City review (2-4 weeks typical). Address any corrections. Receive permit approval. This phase varies most by jurisdiction. Some cities take 2 weeks, others 8+.
Week 5: Excavation
Pool shape is laid out. Excavation takes 1-3 days. Soil is removed (expect trucks). Rough shape of pool emerges. This is exciting but messy. Your yard will be a construction zone.
Ready to Start Your Project?
Schedule a free consultation with our design team.
Book a Consultation Call 818-300-2393
Weeks 6-7: Steel & Plumbing
Rebar cage is tied. Plumbing lines installed. Electrical conduit run. Equipment pad formed. First inspection by city.
Week 8: Gunite/Shotcrete
Pool shell is sprayed. This is the loudest day. Shell needs to cure (water daily for 2 weeks). Rough shape complete.
Weeks 9-11: Tile, Coping, Decking
Waterline tile installed. Coping stones set. Pool deck poured or pavers installed. Equipment installed. Most visible progress happens here.
Weeks 12-14: Plaster & Startup
Interior finish applied. Pool fills with water (24-48 hours). Equipment startup and balancing. Homeowner orientation. First swim!
Final Thoughts
Expect 12-16 weeks total from permit to swimming. Weather delays, inspection schedules, and material availability can extend this. Patience is essential.
Where we build
Build this at your home
We build from Santa Clarita to Long Beach, Thousand Oaks to Riverside, and Orange County down to Mission Viejo. Start with your city:
Frequently Asked Questions
How long does pool construction take?
Typically 12-16 weeks from permit approval to first swim.
What's the loudest part of pool construction?
Gunite/shotcrete day is the loudest. Warn your neighbors.
Topics
- pool construction
- timeline
- process
- what to expect
- pool building
About the author
Remodel Your Vibe Design Team
Written by the design team at Remodel Your Vibe, a licensed ( CSLB #1119054 ), bonded and insured, veteran-owned and family-operated design-build company based in Los Angeles. Our own crews design, permit and build pools, backyards, ADUs and interiors across Greater Los Angeles and Orange County.
Who builds it
- Veteran-owned and family-operated
- Years of experience building across Southern California
- Our own crews build it. One team designs, permits and builds.
Related services
Talk it through with us
Discuss your project with our design team and get expert advice. We call you back within one business day.
Book a Consultation 818-300-2393
Ready to Transform Your Space?
Let's discuss your vision. Schedule a free consultation with our design team and see how we can bring your project to life.
Book a Consultation 818-300-2393
We call you back within one business day.
Continue Reading
Further Reading
Process Guide
Educational
Material Guide
Comparison Guide
All Construction Process guides
End of text part 1 of 1. This page is complete.